Firemen’s Park Nears Finish Line After Delays; August Opening Targeted

Spread the love

After months of anticipation and unforeseen challenges, the major renovation of Firemen’s Park is scheduled for substantial completion by August 11, with a final completion date of August 22, project leaders announced at the Monee Village Board meeting Wednesday.

Engineers and contractors detailed a series of setbacks that have delayed the park’s opening, primarily citing unmarked underground utilities and significant backlogs at ComEd.

“Everyone’s anxious to have Firemen’s Park open and ready and be operational, and we’re getting close,” said Matt Bergher, an engineer with Farnsworth Group, who presented alongside Justin Goslin, president of Piggush Simoneau, Inc. (PSI), and site manager Jason Phillips.

The project team described the park’s subsurface as a maze of unexpected obstacles. “Some of the things have been underground utility lines that are just not marked,” Bergher explained. “And also ones that were not known to exist underneath there just from years and years of building out Firemen’s Park.”

Crews discovered unmarked sanitary laterals, fiber optic lines, and electrical wires that were not in conduit, posing a safety hazard. They also unearthed improperly connected drain pipes and a water main buried less than four feet deep, far shallower than the typical five-foot requirement, which forced a halt to some utility work to ensure future designs met state codes.

“Basically we’ll have all the concrete done minus where that transformer is, middle of next week,” Phillips said. “And then we’ll have to wait for that transformer to be decommissioned to finish that the concrete in that area.”

The most significant external hurdle has been with ComEd. Project leaders said the utility company’s layoffs last year after a failed rate hike request created a massive backlog of work orders.

“We’ve been told hopefully we would have service in advance, but that has delayed some things,” Bergher said. “We’re still waiting on them. They were supposed to be here last Friday. They put us off yet again and we still do not have an answer.”

This delay has forced the construction team to work out of sequence, completing available tasks while waiting for permanent power to be installed. Goslin noted that contingency plans are being developed to use temporary power to irrigate the new fields if necessary.

Another challenge emerged mid-construction when the Monee Historical Society raised concerns about the accessibility of the adjacent Creamery building. The existing mechanical lift has been unreliable, and a request was made to add a permanent ADA-compliant ramp. Because concrete walkways were already poured, adding a concrete ramp now would require costly demolition or concrete pumping.

“We probably had $60-70,000 in just getting the concrete up into the area,” Goslin said. PSI is now exploring more cost-effective alternatives, including a pre-fabricated galvanized steel ramp system similar to those used in stadiums, which would require less site disruption.

Despite the delays, visible progress is being made daily. The storage building and volleyball courts are largely finished, needing only nets. Most concrete work for walkways and paths is expected to be complete within a week. At the baseball field, fences for the batting cages are up, the infield is graded, and backstops are in place. The football fields are graded, with final restoration and seeding planned as one of the last steps to avoid damage from remaining construction traffic.

Work on the interiors of the restroom and concession buildings is also advancing, with finishing elements like wall coverings, flooring, and fixtures being installed. Substantial completion is expected by August 11, which means the park will be functional and usable. The following two weeks, until the August 22 final completion date, will be dedicated to addressing a “punch list” of minor finishing touches.

During the presentation, Trustee Chuck Rakis questioned the fit and finish on the concession stand, pointing to photos showing rust on the bottom of metal panels. Goslin acknowledged the issue, explaining that a drip edge was causing water to flow back under the panels. “Yes, we are addressing that issue,” he assured the board. “We might be pulling that metal up and readjusting that lower flashing.”

Monee Events

10 Dec

Village Board Meeting

December 10, 2025
6:30 pm - 11:59 pm
https://villageofmonee.org/calendar.aspx?EID=1537

Latest News Stories

Screenshot-2025-08-19-at-6.09.01-PM

Peotone School Board Rejects Mandating Live-Streaming in 4-3 Vote

Article Summary: The Peotone school board has opted against requiring its meetings to be live-streamed, finalizing a new committee policy after a 4-3 vote defeated the mandate. The decision followed...
Meeting Briefs

Meeting Summary and Briefs: Peotone Board of Education for August 18, 2025

The Peotone Board of Education’s August 18 meeting was defined by the district’s precarious financial situation. With a projected $4.2 million operating deficit and its borrowing capacity nearly exhausted, the...
Exec Cmte 8.14.25.4

Executive Committee Details Spending of $134 Million in Pandemic Relief Funds

Article Summary: Will County has expended 61% of its $134 million in federal American Rescue Plan Act (ARPA) funds, with significant investments made in infrastructure, health, and economic development. Officials...
Peotone-Committee-8.18.25.1

Facing Budget Crisis, Peotone Committee Questions Athletic Field Project

Committee of the Whole Article Summary: With Peotone School District 207-U on the verge of a financial crisis, board members are questioning the wisdom of moving forward with a long-awaited...
Meeting Briefs

Committee Summary and Briefs: Peotone Board of Education Committee of the Whole

The Peotone School District 207-U is on a collision course with a major financial crisis, which dominated the Board of Education’s committee meeting on August 18. Facing a projected $4.2...
Meeting Briefs

Meeting Summary and Briefs: Crete-Monee School Board for August 12, 2025

The Crete-Monee School District 201-U Board of Education confronted a challenging financial forecast and held a robust debate on arming a district security director during its August 12 meeting. The...
peotone library graphic logo.1

Peotone Library Director’s Salary Set at $75,000 After Annual Evaluation

Article Summary: The Peotone Public Library District Board of Trustees has set Library Director Sarah Ehlers' salary at $75,000 for the upcoming year. The decision was made in a special...
peotone library graphic logo.1

Peotone Library Director’s Salary Set at $75,000 After Annual Evaluation

Article Summary: The Peotone Public Library District Board of Trustees has set Library Director Sarah Ehlers' salary at $75,000 for the upcoming year. The decision was made in a special...
Screenshot 2025-11-26 at 7.32.09 AM

Village Hall to Get $412,000 Fire Sprinkler Replacement After System Failure

Village of Monee Board Meeting | August 13, 2025 Article Summary: Following the failure of the original 1997 fire sprinkler system due to corrosion, the Monee Village Board approved a...
crete-monee school district graphic.6

Crete-Monee Board Adopts School Improvement Plans for 2025-2026

Article Summary: The Crete-Monee Board of Education has approved the 2025-2026 School Improvement Plans (SIPs) for all eight schools in the district. The plans, which are a federal requirement for...
Exec Cmte 8.14.25.3

Executive Committee Considers $12,000 Strategic Planning Initiative with University of St. Francis

Article Summary: The Will County Executive Committee is considering a proposal from the University of St. Francis to lead a six-month, $12,178 strategic planning process. The initiative is aimed at...
crete-monee school district graphic.5

Board Approves Over $4.4 Million for Major Construction Projects

Article Summary: The Crete-Monee School Board authorized payments totaling over $4.4 million for significant construction and renovation work at Crete-Monee High School and Crete Elementary School. The payments cover ongoing...
Exec Cmte 8.14.25.2

Executive Committee Members Decry Roadside Litter, Call for Action Against Garbage Haulers

Article Summary: Will County Executive Committee members expressed frustration over what they described as a worsening problem of litter blowing from garbage trucks across the county. Members called for better...
crete-monee school district graphic.4

District Presses Village of Monee on TIF Expiration, Moves to Sell School Property

Article Summary: Crete-Monee officials are urging the Village of Monee to finalize the expiration of a key tax increment financing (TIF) district before a November deadline to ensure the school...
Ad Hoc.8.12.25.3

Will County Updates Solid Waste Ordinance, Increases Fines and Reporting to Landfill Committee

Article Summary: The Will County Ad-Hoc Ordinance Review Committee advanced an updated solid waste ordinance that doubles the maximum fine for violations and requires the county auditor's annual report to...