Firemen’s Park Nears Finish Line After Delays; August Opening Targeted

Spread the love

After months of anticipation and unforeseen challenges, the major renovation of Firemen’s Park is scheduled for substantial completion by August 11, with a final completion date of August 22, project leaders announced at the Monee Village Board meeting Wednesday.

Engineers and contractors detailed a series of setbacks that have delayed the park’s opening, primarily citing unmarked underground utilities and significant backlogs at ComEd.

“Everyone’s anxious to have Firemen’s Park open and ready and be operational, and we’re getting close,” said Matt Bergher, an engineer with Farnsworth Group, who presented alongside Justin Goslin, president of Piggush Simoneau, Inc. (PSI), and site manager Jason Phillips.

The project team described the park’s subsurface as a maze of unexpected obstacles. “Some of the things have been underground utility lines that are just not marked,” Bergher explained. “And also ones that were not known to exist underneath there just from years and years of building out Firemen’s Park.”

Crews discovered unmarked sanitary laterals, fiber optic lines, and electrical wires that were not in conduit, posing a safety hazard. They also unearthed improperly connected drain pipes and a water main buried less than four feet deep, far shallower than the typical five-foot requirement, which forced a halt to some utility work to ensure future designs met state codes.

“Basically we’ll have all the concrete done minus where that transformer is, middle of next week,” Phillips said. “And then we’ll have to wait for that transformer to be decommissioned to finish that the concrete in that area.”

The most significant external hurdle has been with ComEd. Project leaders said the utility company’s layoffs last year after a failed rate hike request created a massive backlog of work orders.

“We’ve been told hopefully we would have service in advance, but that has delayed some things,” Bergher said. “We’re still waiting on them. They were supposed to be here last Friday. They put us off yet again and we still do not have an answer.”

This delay has forced the construction team to work out of sequence, completing available tasks while waiting for permanent power to be installed. Goslin noted that contingency plans are being developed to use temporary power to irrigate the new fields if necessary.

Another challenge emerged mid-construction when the Monee Historical Society raised concerns about the accessibility of the adjacent Creamery building. The existing mechanical lift has been unreliable, and a request was made to add a permanent ADA-compliant ramp. Because concrete walkways were already poured, adding a concrete ramp now would require costly demolition or concrete pumping.

“We probably had $60-70,000 in just getting the concrete up into the area,” Goslin said. PSI is now exploring more cost-effective alternatives, including a pre-fabricated galvanized steel ramp system similar to those used in stadiums, which would require less site disruption.

Despite the delays, visible progress is being made daily. The storage building and volleyball courts are largely finished, needing only nets. Most concrete work for walkways and paths is expected to be complete within a week. At the baseball field, fences for the batting cages are up, the infield is graded, and backstops are in place. The football fields are graded, with final restoration and seeding planned as one of the last steps to avoid damage from remaining construction traffic.

Work on the interiors of the restroom and concession buildings is also advancing, with finishing elements like wall coverings, flooring, and fixtures being installed. Substantial completion is expected by August 11, which means the park will be functional and usable. The following two weeks, until the August 22 final completion date, will be dedicated to addressing a “punch list” of minor finishing touches.

During the presentation, Trustee Chuck Rakis questioned the fit and finish on the concession stand, pointing to photos showing rust on the bottom of metal panels. Goslin acknowledged the issue, explaining that a drip edge was causing water to flow back under the panels. “Yes, we are addressing that issue,” he assured the board. “We might be pulling that metal up and readjusting that lower flashing.”

Monee Events

10 Dec

Village Board Meeting

December 10, 2025
6:30 pm - 11:59 pm
https://villageofmonee.org/calendar.aspx?EID=1537

Latest News Stories

WCO Board Aug 21.1

Will County Executive Proposes $791 Million Budget Focused on Stability Amidst Economic Uncertainty

Article Summary: Will County Executive Jennifer Bertino-Tarrant presented a balanced $791 million budget proposal for Fiscal Year 2026 that aims to maintain services and prepare for potential economic challenges without...
Planning & Zoning Graphic.3

Will County P&Z: Washington Township Lot Variance Granted

A variance to reduce the minimum lot area from 10 acres to 5 acres was unanimously approved for a property at 1444 E. Corning Road in Washington Township. The owner,...

Will County P&Z: Washington Township Lot Variance Granted

A variance to reduce the minimum lot area from 10 acres to 5 acres was unanimously approved for a property at 1444 E. Corning Road in Washington Township. The owner,...
solar panels photovoltaics in solar farm

Will County P&Z Approves Crete Solar Farm, Overruling Township’s General Opposition

Article Summary: The Will County Planning and Zoning Commission recommended approval for a new commercial solar farm in Crete Township, moving the project forward despite being informed by staff of...
P&Z 8.19.25

Will County Board Approves Controversial Recovery Retreat in Crete Township Amid Strong Resident Opposition

Article Summary: The Will County Planning and Zoning Commission approved a special use permit for a long-term residential recovery program on a 68-acre horse farm, despite vocal opposition from Crete...

Will County P&Z: Green Garden Township Variances Granted in Monee

Roy F. Erikson received unanimous approval for two variances for his property at 26409 S. 80th Avenue in Monee. The Will County Planning and Zonning Commission approved reducing the minimum...

Will County P&Z: Manhattan Township Rezoning Approved

The Will County Planning and Zonning Commission unanimously approved a map amendment for a vacant property on South Kankakee Street in Manhattan Township. The request, brought by James and Julie...
Planning & Zoning Graphic.4

Will County P&Z: Green Garden Township Rezoning Approved Amid Concerns Over Lack of a Final Plan

Article Summary: The Will County Planning and Zoning Commission unanimously approved rezoning a large agricultural parcel in Green Garden Township for potential residential development, despite a township official expressing concern...
Two orange map markers on city map

Zoning Commission Overrules Staff, Approves Greeen Garden Twp Variance for 3-Acre Agricultural Lot

Article Summary: The Will County Planning and Zoning Commission approved a variance for a 3-acre lot in an agricultural zone, going against a staff recommendation to deny the request in...
Monee Township Graphic.3

Monee Township Board Authorizes $300,000 Loan for Food Pantry Construction

Monee Township Board Meeting | July 2025 Article Summary: The Monee Township Board approved a measure allowing the Supervisor to secure a loan of up to $300,000 to complete the construction...
Screenshot 2025-11-26 at 7.32.27 AM

Monee Acquires Properties, Postpones Governor’s Highway Bid

Village of Monee Board Meeting | August 13, 2025 Article Summary: The Village of Monee moved forward with strategic real estate acquisitions on Monee-Manhattan Road but decided to postpone action...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Executive Committee for August 14, 2025

The Will County Board Executive Committee received a comprehensive update on the county's expenditure of $134 million in federal ARPA pandemic relief funds, learning that 61% of the total has...
Peotone-Committee-8.18.25.2

Peotone Schools Face ‘Fiscal Cliff,’ Board Considers School Closures and New Construction

Committee of the Whole Article Summary: Facing a severe financial crisis and a rapidly approaching deadline from a major road project, the Peotone School District 207-U board is now seriously...
Screenshot-2025-08-19-at-6.16.25-PM

Committee of the Whole Eyes School Closures and New Construction Amid Budget Crisis

Committee of the Whole Article Summary: Facing a severe financial crisis with a projected $4.2 million operating deficit, the Peotone School District 207-U board is now seriously exploring the closure...
Screenshot-2025-08-19-at-6.11.05-PM

Acting, Consulting Superintendents to Lead Peotone Schools During Owens’ Absence

Article Summary: Superintendent Brandon Owens is recuperating at home following a vehicle accident, prompting the Peotone Board of Education to establish an interim leadership team. Assistant Superintendent Carole Zurales will...