Firemen’s Park Nears Finish Line After Delays; August Opening Targeted

Spread the love

After months of anticipation and unforeseen challenges, the major renovation of Firemen’s Park is scheduled for substantial completion by August 11, with a final completion date of August 22, project leaders announced at the Monee Village Board meeting Wednesday.

Engineers and contractors detailed a series of setbacks that have delayed the park’s opening, primarily citing unmarked underground utilities and significant backlogs at ComEd.

“Everyone’s anxious to have Firemen’s Park open and ready and be operational, and we’re getting close,” said Matt Bergher, an engineer with Farnsworth Group, who presented alongside Justin Goslin, president of Piggush Simoneau, Inc. (PSI), and site manager Jason Phillips.

The project team described the park’s subsurface as a maze of unexpected obstacles. “Some of the things have been underground utility lines that are just not marked,” Bergher explained. “And also ones that were not known to exist underneath there just from years and years of building out Firemen’s Park.”

Crews discovered unmarked sanitary laterals, fiber optic lines, and electrical wires that were not in conduit, posing a safety hazard. They also unearthed improperly connected drain pipes and a water main buried less than four feet deep, far shallower than the typical five-foot requirement, which forced a halt to some utility work to ensure future designs met state codes.

“Basically we’ll have all the concrete done minus where that transformer is, middle of next week,” Phillips said. “And then we’ll have to wait for that transformer to be decommissioned to finish that the concrete in that area.”

The most significant external hurdle has been with ComEd. Project leaders said the utility company’s layoffs last year after a failed rate hike request created a massive backlog of work orders.

“We’ve been told hopefully we would have service in advance, but that has delayed some things,” Bergher said. “We’re still waiting on them. They were supposed to be here last Friday. They put us off yet again and we still do not have an answer.”

This delay has forced the construction team to work out of sequence, completing available tasks while waiting for permanent power to be installed. Goslin noted that contingency plans are being developed to use temporary power to irrigate the new fields if necessary.

Another challenge emerged mid-construction when the Monee Historical Society raised concerns about the accessibility of the adjacent Creamery building. The existing mechanical lift has been unreliable, and a request was made to add a permanent ADA-compliant ramp. Because concrete walkways were already poured, adding a concrete ramp now would require costly demolition or concrete pumping.

“We probably had $60-70,000 in just getting the concrete up into the area,” Goslin said. PSI is now exploring more cost-effective alternatives, including a pre-fabricated galvanized steel ramp system similar to those used in stadiums, which would require less site disruption.

Despite the delays, visible progress is being made daily. The storage building and volleyball courts are largely finished, needing only nets. Most concrete work for walkways and paths is expected to be complete within a week. At the baseball field, fences for the batting cages are up, the infield is graded, and backstops are in place. The football fields are graded, with final restoration and seeding planned as one of the last steps to avoid damage from remaining construction traffic.

Work on the interiors of the restroom and concession buildings is also advancing, with finishing elements like wall coverings, flooring, and fixtures being installed. Substantial completion is expected by August 11, which means the park will be functional and usable. The following two weeks, until the August 22 final completion date, will be dedicated to addressing a “punch list” of minor finishing touches.

During the presentation, Trustee Chuck Rakis questioned the fit and finish on the concession stand, pointing to photos showing rust on the bottom of metal panels. Goslin acknowledged the issue, explaining that a drip edge was causing water to flow back under the panels. “Yes, we are addressing that issue,” he assured the board. “We might be pulling that metal up and readjusting that lower flashing.”

Monee Events

10 Dec

Village Board Meeting

December 10, 2025
6:30 pm - 11:59 pm
https://villageofmonee.org/calendar.aspx?EID=1537

Latest News Stories

Meeting-Briefs

Meeting Summary and Briefs: Crete-Monee School District 201-U for September 2025

Crete-Monee School District 201-U Meeting | September 2025 Overall Meeting SummaryThe Crete-Monee School District 201-U Board of Education met on Tuesday, September 16, 2025, to conduct essential business including the...
Screenshot 2025-11-26 at 7.54.47 AM

Monee Considers Major Solar Farm Proposal with $100,000 Incentive

Village of Monee Board Meeting | September 24, 2025 Article Summary: Representatives from Earthrise Energy presented plans for "Plum Valley Solar," a massive 2,400-acre solar facility proposed for the Monee...
Screenshot 2025-11-25 at 9.39.35 PM

Attendance Matters’ Campaign Kicks Off to Combat Truancy

Crete-Monee School District 201-U Meeting | September 2025 Article Summary: The district introduced a new "Attendance Matters" campaign led by Truancy Officer Eric Green, aimed at proactively improving student attendance...
Screenshot 2025-11-25 at 9.39.24 PM

District Launches ‘ParentSquare’ to Unify School Communications

Crete-Monee School District 201-U Meeting | September 2025 Article Summary: Crete-Monee School District 201-U is rolling out ParentSquare, a new unified communication platform designed to replace multiple existing apps and...
Monee Township Logo.1

Public Hearings Set for I-57 Freight Route and Monee TIF District

Monee Township Board Meeting | August 2025 Article Summary: Local and county officials alerted the Monee Township Board to upcoming public hearings regarding major regional developments. The hearings concern a proposed...
Meeting Briefs

Meeting Summary and Briefs: Village of Monee Board for September 10, 2025

Village of Monee Board Meeting | September 10, 2025 Meeting Summary: The Monee Village Board of Trustees met on Wednesday, September 10, 2025, for a session focused on infrastructure spending...
Screenshot 2025-11-25 at 9.39.05 PM

Board Awards $4 Million Contract for Middle School Renovations

Crete-Monee School District 201-U Meeting | September 2025 Article Summary: The Board of Education awarded a $4 million contract to BEAR Construction for renovations at Crete-Monee Middle School, a project...
Monee Township Graphic.4

Monee Township Food Pantry Expansion Phase 2 Pushed to 2026

Monee Township Board Meeting | August 2025 Article Summary: The Monee Township Board announced a significant schedule adjustment for the ongoing food pantry expansion project. While the first phase is complete,...
peotone library graphic logo.1

Peotone Library to Install $25,000 Smart Lockers in Monee to Expand Service

Article Summary: The Peotone Public Library District is moving forward with a plan to purchase and install a $25,000 smart locker system in Monee, providing a convenient pickup point for residents...
Screenshot 2025-11-25 at 9.38.51 PM

Crete-Monee Board Approves 2025-2026 Budget with Focus on Capital Projects

Crete-Monee School District 201-U Meeting | September 2025 Article Summary: The Crete-Monee School District 201-U Board of Education voted to adopt the fiscal year 2025-2026 budget, which projects a deficit...
Screenshot 2025-11-26 at 7.49.21 AM

Village Officials Celebrate Fall Fest Success; Reappoint Key Staff

Village of Monee Board Meeting | September 10, 2025 Article Summary: Following a successful Fall Fest, Monee officials praised village staff and volunteers for a safe and well-attended event. The...
Screenshot 2025-11-26 at 7.49.14 AM

Monee Approves Nearly $700,000 for Sidewalks and Drainage Improvements

Village of Monee Board Meeting | September 10, 2025 Article Summary: The Monee Village Board awarded two major infrastructure contracts totaling nearly $700,000 to address sidewalk connectivity and pond remediation....
Screenshot 2025-11-26 at 7.49.02 AM

Monee Board Rejects “Up Front” Cash Requests from Hotel Developer

Village of Monee Board Meeting | September 10, 2025 Article Summary: The Monee Village Board reached a consensus to reject new terms proposed by the developer of the Quality Inn...
Meeting Briefs

Meeting Summary and Briefs: Village of Monee Board for August 27, 2025

Village of Monee Board Meeting | August 27, 2025 Meeting Summary:The Monee Village Board of Trustees met on Wednesday, August 27, 2025, to address significant financial and development matters. The...
Monee Graphic.1

Board Approves $1.2 Million Payout for Road Construction and New Park Accessibility Lift

Village of Monee Board Meeting | August 27, 2025 Article Summary:The Monee Village Board authorized a payment of over $1.2 million for the ongoing reconstruction of Industrial Drive and Cleveland...