After months of anticipation and unforeseen challenges, the major renovation of Firemen’s Park is scheduled for substantial completion by August 11, with a final completion date of August 22, project leaders announced at the Monee Village Board meeting Wednesday.

Engineers and contractors detailed a series of setbacks that have delayed the park’s opening, primarily citing unmarked underground utilities and significant backlogs at ComEd.

“Everyone’s anxious to have Firemen’s Park open and ready and be operational, and we’re getting close,” said Matt Bergher, an engineer with Farnsworth Group, who presented alongside Justin Goslin, president of Piggush Simoneau, Inc. (PSI), and site manager Jason Phillips.

The project team described the park’s subsurface as a maze of unexpected obstacles. “Some of the things have been underground utility lines that are just not marked,” Bergher explained. “And also ones that were not known to exist underneath there just from years and years of building out Firemen’s Park.”

Crews discovered unmarked sanitary laterals, fiber optic lines, and electrical wires that were not in conduit, posing a safety hazard. They also unearthed improperly connected drain pipes and a water main buried less than four feet deep, far shallower than the typical five-foot requirement, which forced a halt to some utility work to ensure future designs met state codes.

“Basically we’ll have all the concrete done minus where that transformer is, middle of next week,” Phillips said. “And then we’ll have to wait for that transformer to be decommissioned to finish that the concrete in that area.”

The most significant external hurdle has been with ComEd. Project leaders said the utility company’s layoffs last year after a failed rate hike request created a massive backlog of work orders.

“We’ve been told hopefully we would have service in advance, but that has delayed some things,” Bergher said. “We’re still waiting on them. They were supposed to be here last Friday. They put us off yet again and we still do not have an answer.”

This delay has forced the construction team to work out of sequence, completing available tasks while waiting for permanent power to be installed. Goslin noted that contingency plans are being developed to use temporary power to irrigate the new fields if necessary.

Another challenge emerged mid-construction when the Monee Historical Society raised concerns about the accessibility of the adjacent Creamery building. The existing mechanical lift has been unreliable, and a request was made to add a permanent ADA-compliant ramp. Because concrete walkways were already poured, adding a concrete ramp now would require costly demolition or concrete pumping.

“We probably had $60-70,000 in just getting the concrete up into the area,” Goslin said. PSI is now exploring more cost-effective alternatives, including a pre-fabricated galvanized steel ramp system similar to those used in stadiums, which would require less site disruption.

Despite the delays, visible progress is being made daily. The storage building and volleyball courts are largely finished, needing only nets. Most concrete work for walkways and paths is expected to be complete within a week. At the baseball field, fences for the batting cages are up, the infield is graded, and backstops are in place. The football fields are graded, with final restoration and seeding planned as one of the last steps to avoid damage from remaining construction traffic.

Work on the interiors of the restroom and concession buildings is also advancing, with finishing elements like wall coverings, flooring, and fixtures being installed. Substantial completion is expected by August 11, which means the park will be functional and usable. The following two weeks, until the August 22 final completion date, will be dedicated to addressing a “punch list” of minor finishing touches.

During the presentation, Trustee Chuck Rakis questioned the fit and finish on the concession stand, pointing to photos showing rust on the bottom of metal panels. Goslin acknowledged the issue, explaining that a drip edge was causing water to flow back under the panels. “Yes, we are addressing that issue,” he assured the board. “We might be pulling that metal up and readjusting that lower flashing.”

Monee Events

10 Dec

Village Board Meeting

December 10, 2025
6:30 pm - 11:59 pm
https://villageofmonee.org/calendar.aspx?EID=1537

Latest News Stories

Screenshot 2025-11-26 at 8.02.29 AM

Monee Dissolves TIF District 3, Transfers $1 Million Surplus

Village of Monee Board Meeting | October 8, 2025 Article Summary: After more than 23 years, the Village of Monee has formally dissolved Tax Increment Financing (TIF) District 3. The...
Screenshot 2025-10-10 at 11.39.54 AM

Committee Advances 50% Increase in Mental Health Levy on 4-3 Vote

Will County Finance Committee Meeting October 7, 2025 Article Summary: The Will County Finance Committee on Tuesday narrowly approved a proposed $12 million levy for the Community Mental Health Board,...
Screenshot 2025-10-10 at 11.19.48 AM

Will County Poised to Launch Major Mental Health Initiative Based on Joliet Program’s Success

Will County Public Health & Safety Committee Meeting October 2, 2025 Article Summary: The Will County Board Public Health & Safety Committee on Thursday considered establishing "Will County CARES," a...
Screenshot 2025-10-10 at 12.05.35 PM

Looming State Energy Bill Threatens to Further Limit County Control Over Solar and Wind Projects

Will County Legislative Committee Meeting October 7, 2025 Article Summary: A state energy bill likely to be considered during the fall veto session or next spring could further strip Will...
Screenshot 2025-10-10 at 11.52.31 AM

Controversial Immigrant Rights Resolution Postponed by Will County Board After Heated Debate

Will County Executive Committee Meeting October 9, 2025 Article Summary: The Will County Executive Committee voted to indefinitely postpone a contentious resolution titled "Declaring Will County's Commitment to Ensure Communities...
Screenshot 2025-10-10 at 11.39.50 AM

Will County’s Gas-to-Energy Plant Reports Nearly $460,000 Net Loss Amid Operational Setbacks

Will County Finance Committee Meeting October 7, 2025 Article Summary: Will County's Renewable Natural Gas (RNG) plant at the county landfill posted a net loss of nearly $460,000 for the...
Screenshot 2025-10-10 at 11.36.47 AM

Will County to Draft First-Ever Policy on Artificial Intelligence Use

Will County Capital Improvements & IT Committee Meeting October 7, 2025 Article Summary: The Will County Board's Capital Improvements & IT Committee has initiated the process of drafting a comprehensive...
Screenshot 2025-10-10 at 11.20.18 AM

Will County Sees 50% Drop in Opioid Deaths, But Alarming Rise in Suicides

Will County Public Health & Safety Committee Meeting October 2, 2025 Article Summary: Will County is experiencing a dramatic 50% reduction in opioid overdose deaths compared to last year, a...
Screenshot 2025-10-10 at 11.52.52 AM

Will County Board Backs Effort to Rename ‘Stigmatizing’ Chicago Sanitary and Ship Canal

Will County Executive Committee Meeting October 9, 2025 Article Summary: The Will County Board has thrown its support behind a regional effort to rename the Chicago Sanitary and Ship Canal,...
Screenshot 2025-10-10 at 12.12.04 PM

Access Will County Dial-a-Ride on Track for Full County-Wide Service in 2026

Will County Public Works & Transportation Committee Meeting October 7, 2025 Article Summary: The Access Will County dial-a-ride program is set for a major expansion in 2026, with plans to...
WCO 2025-09-27 at 9.04.36 AM

Divided Will County Board Authorizes Condemnation for 143rd Street Widening

Article Summary: Following intense debate and emotional public testimony, the Will County Board narrowly approved a resolution to begin condemnation proceedings for the controversial widening of 143rd Street in Homer...
Screenshot 2025-10-10 at 11.39.44 AM

Will County Committee Approves Preliminary $161.6M Tax Levy on Split Vote Amid Heated Debate Over Spending

Will County Finance Committee Meeting October 7, 2025 Article Summary: The Will County Finance Committee on Tuesday narrowly approved a preliminary $161.6 million property tax levy for 2025, which projects...
Screenshot 2025-10-10 at 11.36.42 AM

Will County Eyes Major Overhaul to Consolidate Scattered Government Offices

Will County Capital Improvements & IT Committee Meeting October 7, 2025 Article Summary: Will County officials are formally debating a new facilities master plan to address aging buildings and dozens...
Screenshot 2025-11-26 at 8.02.18 AM

Monee Approves $55,000 for Lighting Upgrades and Nearly $290,000 for Sidewalks

Village of Monee Board Meeting | October 8, 2025 Article Summary: The Monee Village Board authorized significant infrastructure payments, including the final payout for lighting improvements on Monee Manhattan Road...
Screenshot 2025-10-10 at 11.20.27 AM

Sheriff’s Office Reports Crime Down 10%, Cites Body Cam Footage as Main Challenge of Safety Act

Will County Public Health & Safety Committee Meeting October 2, 2025 Article Summary: The Will County Sheriff's Office reported a nearly 10% overall drop in crime compared to the same...