Monee VB July 9

Firemen’s Park Nears Finish Line After Delays; August Opening Targeted

Spread the love

After months of anticipation and unforeseen challenges, the major renovation of Firemen’s Park is scheduled for substantial completion by August 11, with a final completion date of August 22, project leaders announced at the Monee Village Board meeting Wednesday.

Engineers and contractors detailed a series of setbacks that have delayed the park’s opening, primarily citing unmarked underground utilities and significant backlogs at ComEd.

“Everyone’s anxious to have Firemen’s Park open and ready and be operational, and we’re getting close,” said Matt Bergher, an engineer with Farnsworth Group, who presented alongside Justin Goslin, president of Piggush Simoneau, Inc. (PSI), and site manager Jason Phillips.

The project team described the park’s subsurface as a maze of unexpected obstacles. “Some of the things have been underground utility lines that are just not marked,” Bergher explained. “And also ones that were not known to exist underneath there just from years and years of building out Firemen’s Park.”

Crews discovered unmarked sanitary laterals, fiber optic lines, and electrical wires that were not in conduit, posing a safety hazard. They also unearthed improperly connected drain pipes and a water main buried less than four feet deep, far shallower than the typical five-foot requirement, which forced a halt to some utility work to ensure future designs met state codes.

“Basically we’ll have all the concrete done minus where that transformer is, middle of next week,” Phillips said. “And then we’ll have to wait for that transformer to be decommissioned to finish that the concrete in that area.”

The most significant external hurdle has been with ComEd. Project leaders said the utility company’s layoffs last year after a failed rate hike request created a massive backlog of work orders.

“We’ve been told hopefully we would have service in advance, but that has delayed some things,” Bergher said. “We’re still waiting on them. They were supposed to be here last Friday. They put us off yet again and we still do not have an answer.”

This delay has forced the construction team to work out of sequence, completing available tasks while waiting for permanent power to be installed. Goslin noted that contingency plans are being developed to use temporary power to irrigate the new fields if necessary.

Another challenge emerged mid-construction when the Monee Historical Society raised concerns about the accessibility of the adjacent Creamery building. The existing mechanical lift has been unreliable, and a request was made to add a permanent ADA-compliant ramp. Because concrete walkways were already poured, adding a concrete ramp now would require costly demolition or concrete pumping.

“We probably had $60-70,000 in just getting the concrete up into the area,” Goslin said. PSI is now exploring more cost-effective alternatives, including a pre-fabricated galvanized steel ramp system similar to those used in stadiums, which would require less site disruption.

Despite the delays, visible progress is being made daily. The storage building and volleyball courts are largely finished, needing only nets. Most concrete work for walkways and paths is expected to be complete within a week. At the baseball field, fences for the batting cages are up, the infield is graded, and backstops are in place. The football fields are graded, with final restoration and seeding planned as one of the last steps to avoid damage from remaining construction traffic.

Work on the interiors of the restroom and concession buildings is also advancing, with finishing elements like wall coverings, flooring, and fixtures being installed. Substantial completion is expected by August 11, which means the park will be functional and usable. The following two weeks, until the August 22 final completion date, will be dedicated to addressing a “punch list” of minor finishing touches.

During the presentation, Trustee Chuck Rakis questioned the fit and finish on the concession stand, pointing to photos showing rust on the bottom of metal panels. Goslin acknowledged the issue, explaining that a drip edge was causing water to flow back under the panels. “Yes, we are addressing that issue,” he assured the board. “We might be pulling that metal up and readjusting that lower flashing.”

Latest News Stories

Will County Board Graphic.01

Millions Approved for Will County Highway and Road Infrastructure Projects

Will County Board Meeting | April 16, 2026 Article Summary: The Will County Board authorized nearly $4.3 million in road improvement contracts, targeting key corridors including Francis Road, Renwick Road,...
Illinoisans may soon need registration, title, license to use e-bikes, scooters

Illinoisans may soon need registration, title, license to use e-bikes, scooters

By Sean Reed | The Center SquareThe Center Square (The Center Square) – Illinoisans may soon be required to register their e-bikes, motorized scooters and other various modes of transport...
Crete Monee Warriors Baseball Graphic

Quaderer Strikes Out Nine as Crete-Monee Baseball Cruises Past Argo 9-1

The Crete-Monee varsity baseball team relied on a masterful complete-game pitching performance from junior Keegan Quaderer and consistent offensive pressure to defeat Argo 9-1 on Wednesday afternoon. In a non-conference...
Pritzker’s commission report pushes for local investigations of federal 'brutality'

Pritzker’s commission report pushes for local investigations of federal ‘brutality’

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – Gov. J.B. Pritzker’s Illinois Accountability Commission has released its report on alleged abuses by federal immigration law...
Illinois mulls change allowing pension investment in anti-Israel companies

Illinois mulls change allowing pension investment in anti-Israel companies

By Sean Reed | The Center SquareThe Center Square (The Center Square) – Multiple speakers shared personal stories Thursday from the conflict between Israeli forces and Palestinians in an effort...
Crete Monee School Board Graphic.2

Crete-Monee Board Considers Official ‘Statements of Support’ for Grieving Families

Crete-Monee Board of Education Meeting | April 14, 2026 Article Summary: Following a recent tragedy involving the deaths of three local children and their grandfather, the Crete-Monee Board of Education is...
Will County Board Graphic.04

Board Establishes New Regulations and Fees for Wireless Telecommunication Facilities

Will County Board Meeting | April 16, 2026 Article Summary: In response to the state's Small Wireless Facilities Deployment Act, the Will County Board passed Ordinance 26-134 to manage the...
Screenshot 2026-04-25 at 9.09.23 AM

Monee Board Explores Farmland Preservation Program Amid Growing Concerns Over Solar Development

Monee Village Board Meeting | April 22, 2026 Article Summary: The Monee Village Board engaged in a lengthy discussion with Will County Planning and Zoning Commissioner John Kiefner about creating a...
Crete Monee School Board Graphic.1

Crete-Monee Unveils New Community Partnership Initiative for District Sponsorships

Crete-Monee Board of Education Meeting | April 14, 2026 Article Summary: The Crete-Monee Board of Education on Tuesday reviewed a new sponsorship framework designed to generate revenue through community and business...
Screenshot 2026-04-25 at 9.01.34 AM

Meeting Summary and Briefs: Monee Village Board for April 15, 2026

Monee Village Board Meeting | April 15, 2026 The Monee Village Board held a special meeting on Wednesday evening dedicated entirely to finalizing the draft Fiscal Year 2027 budget. The...
Joseph House

Historic Joseph Perry House in Crete Granted Landmark Status

Will County Board Meeting | April 16, 2026 Article Summary: The Will County Board officially designated the Joseph Ferris Perry House in Crete Township as a historical landmark, protecting the...
Screenshot 2026-04-25 at 9.01.34 AM

Monee Restores $25,000 Funding for Historical Society Following Public Appeal

Monee Village Board Meeting | April 15, 2026 Article Summary: Following an outpouring of public support, the Monee Village Board voted to restore $25,000 in funding for the Monee Historical Society...
Crete Monee Warriors Baseball Graphic

Love Goes the Distance as Crete-Monee Tops Thornton Fractional South 8-2

The Crete-Monee varsity baseball team leaned on a stellar complete-game performance from sophomore pitcher Wyatt Love to secure an 8-2 non-conference victory over Thornton Fractional South on Saturday. Supported by...
Crete Monee School Board Graphic.2

Crete-Monee Sixth Grader Advances to Scripps National Spelling Bee in D.C.

Crete-Monee Board of Education Meeting | April 14, 2026 Article Summary: The Crete-Monee Board of Education celebrated 11-year-old Kingston McGee, who recently became the first student in the middle school's history...
Will County Board Graphic.02

Will County Passes Comprehensive Adult Entertainment Ordinance

Will County Board Meeting | April 16, 2026 Article Summary: The Will County Board passed Ordinance 26-133, enacting Chapter 119 of the Business Regulations to establish rigorous licensing, operational, and...