Firemen’s Park Nears Finish Line After Delays; August Opening Targeted

Spread the love

After months of anticipation and unforeseen challenges, the major renovation of Firemen’s Park is scheduled for substantial completion by August 11, with a final completion date of August 22, project leaders announced at the Monee Village Board meeting Wednesday.

Engineers and contractors detailed a series of setbacks that have delayed the park’s opening, primarily citing unmarked underground utilities and significant backlogs at ComEd.

“Everyone’s anxious to have Firemen’s Park open and ready and be operational, and we’re getting close,” said Matt Bergher, an engineer with Farnsworth Group, who presented alongside Justin Goslin, president of Piggush Simoneau, Inc. (PSI), and site manager Jason Phillips.

The project team described the park’s subsurface as a maze of unexpected obstacles. “Some of the things have been underground utility lines that are just not marked,” Bergher explained. “And also ones that were not known to exist underneath there just from years and years of building out Firemen’s Park.”

Crews discovered unmarked sanitary laterals, fiber optic lines, and electrical wires that were not in conduit, posing a safety hazard. They also unearthed improperly connected drain pipes and a water main buried less than four feet deep, far shallower than the typical five-foot requirement, which forced a halt to some utility work to ensure future designs met state codes.

“Basically we’ll have all the concrete done minus where that transformer is, middle of next week,” Phillips said. “And then we’ll have to wait for that transformer to be decommissioned to finish that the concrete in that area.”

The most significant external hurdle has been with ComEd. Project leaders said the utility company’s layoffs last year after a failed rate hike request created a massive backlog of work orders.

“We’ve been told hopefully we would have service in advance, but that has delayed some things,” Bergher said. “We’re still waiting on them. They were supposed to be here last Friday. They put us off yet again and we still do not have an answer.”

This delay has forced the construction team to work out of sequence, completing available tasks while waiting for permanent power to be installed. Goslin noted that contingency plans are being developed to use temporary power to irrigate the new fields if necessary.

Another challenge emerged mid-construction when the Monee Historical Society raised concerns about the accessibility of the adjacent Creamery building. The existing mechanical lift has been unreliable, and a request was made to add a permanent ADA-compliant ramp. Because concrete walkways were already poured, adding a concrete ramp now would require costly demolition or concrete pumping.

“We probably had $60-70,000 in just getting the concrete up into the area,” Goslin said. PSI is now exploring more cost-effective alternatives, including a pre-fabricated galvanized steel ramp system similar to those used in stadiums, which would require less site disruption.

Despite the delays, visible progress is being made daily. The storage building and volleyball courts are largely finished, needing only nets. Most concrete work for walkways and paths is expected to be complete within a week. At the baseball field, fences for the batting cages are up, the infield is graded, and backstops are in place. The football fields are graded, with final restoration and seeding planned as one of the last steps to avoid damage from remaining construction traffic.

Work on the interiors of the restroom and concession buildings is also advancing, with finishing elements like wall coverings, flooring, and fixtures being installed. Substantial completion is expected by August 11, which means the park will be functional and usable. The following two weeks, until the August 22 final completion date, will be dedicated to addressing a “punch list” of minor finishing touches.

During the presentation, Trustee Chuck Rakis questioned the fit and finish on the concession stand, pointing to photos showing rust on the bottom of metal panels. Goslin acknowledged the issue, explaining that a drip edge was causing water to flow back under the panels. “Yes, we are addressing that issue,” he assured the board. “We might be pulling that metal up and readjusting that lower flashing.”

Monee Events

10 Dec

Village Board Meeting

December 10, 2025
6:30 pm - 11:59 pm
https://villageofmonee.org/calendar.aspx?EID=1537

Latest News Stories

Screenshot 2025-11-26 at 8.02.43 AM

New Public Works Facility to Host Grand Opening

Village of Monee Board Meeting | October 8, 2025 Article Summary: Monee officials are inviting the public to tour the newly completed Department of Public Works facility. A grand opening...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Legislative Committee for October 7, 2025

The Will County Legislative Committee held a long and contentious meeting on Tuesday, October 7, 2025, highlighted by the narrow 4-3 passage of a controversial resolution supporting protections for immigrant...
Screenshot 2025-10-10 at 12.05.55 PM

Will County Board Committee Passes Contentious ‘Live and Work Without Fear’ Resolution on 4-3 Vote

Will County Legislative Committee Meeting October 7, 2025 Article Summary: The Will County Legislative Committee on Tuesday narrowly passed a controversial resolution affirming the county's commitment to ensuring all residents...
Meeting Briefs

Will County Awards $10.4 Million Contract for Bell Road Widening in Homer Glen Area

Will County Public Works & Transportation Committee Meeting October 7, 2025 Article Summary: The Will County Public Works & Transportation Committee on Tuesday confirmed the award of a $10.4 million...
Screenshot 2025-11-26 at 8.02.35 AM

Monee Proceeds with Land Acquisition for Road Realignment; Secures $560k Grant

Village of Monee Board Meeting | October 8, 2025 Article Summary: The Monee Village Board passed a new ordinance authorizing the purchase of real estate at Cleveland Avenue and Monee...
Screenshot 2025-10-10 at 12.12.16 PM

Meeting Summary and Briefs: Will County Public Works & Transportation Committee for October 7, 2025

The Will County Public Works & Transportation Committee on Tuesday, October 7, 2025, approved a major construction contract and reviewed extensive plans for both county and state transportation initiatives. The...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Finance Committee for October 7, 2025

The Will County Finance Committee on Tuesday, October 7, 2025, held a contentious meeting centered on the county’s finances, narrowly approving a preliminary $161.6 million county-wide tax levy on a...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Capital Improvements & IT Committee for October 7, 2025

The Will County Capital Improvements & IT Committee spent the bulk of its meeting on Tuesday, October 7, 2025, discussing the county’s long-term facilities master plan. Faced with an aging...
peotone library graphic logo.4

Monee and Peotone Library Partner on New Smart Locker Location and Costs

Article Summary: The Peotone Public Library and the Village of Monee have tentatively selected the circle drive at the Monee Parks and Recreation building as the site for a new library...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Public Health & Safety Committee for October 2, 2025

The Will County Public Health & Safety Committee on Thursday, October 2, 2025, heard a mix of alarming and encouraging public health news, as officials reported a dramatic 50% drop...
Screenshot 2025-10-10 at 12.05.41 PM

Will County Shapes 2026 Federal Agenda, Prioritizing Health, Housing, and Workforce Funding

Will County Legislative Committee Meeting October 7, 2025 Article Summary: The Will County Legislative Committee on Tuesday began finalizing its 2026 Federal Legislative Agenda, formally adopting key priorities that include...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Executive Committee for October 9, 2025

The Will County Board’s Executive Committee held a contentious meeting on Thursday, October 9, 2025, dominated by debates over public access and a controversial resolution concerning immigrant rights. A proposal...
Screenshot 2025-10-10 at 11.36.53 AM

Renovations at Veterans Assistance Commission and Court Annex on Track for Winter Completion

Will County Capital Improvements & IT Committee Meeting October 7, 2025 Article Summary: Will County's new Veterans Assistance Commission facility in Joliet is projected to be completed by December, while...
Screenshot 2025-10-10 at 11.20.34 AM

Will County Considers First Update to Wastewater Ordinance Since 2016

Will County Public Health & Safety Committee Meeting October 2, 2025 Article Summary: Will County is preparing to update its ordinance governing private wastewater systems, with proposed changes including the...
Screenshot 2025-10-10 at 12.12.11 PM

IDOT Plans to Invest Over $1.3 Billion in Will County Roads Through 2031

Will County Public Works & Transportation Committee Meeting October 7, 2025 Article Summary: The Illinois Department of Transportation (IDOT) has allocated over $1.3 billion for road and bridge projects in...