Firemen’s Park Nears Finish Line After Delays; August Opening Targeted

Spread the love

After months of anticipation and unforeseen challenges, the major renovation of Firemen’s Park is scheduled for substantial completion by August 11, with a final completion date of August 22, project leaders announced at the Monee Village Board meeting Wednesday.

Engineers and contractors detailed a series of setbacks that have delayed the park’s opening, primarily citing unmarked underground utilities and significant backlogs at ComEd.

“Everyone’s anxious to have Firemen’s Park open and ready and be operational, and we’re getting close,” said Matt Bergher, an engineer with Farnsworth Group, who presented alongside Justin Goslin, president of Piggush Simoneau, Inc. (PSI), and site manager Jason Phillips.

The project team described the park’s subsurface as a maze of unexpected obstacles. “Some of the things have been underground utility lines that are just not marked,” Bergher explained. “And also ones that were not known to exist underneath there just from years and years of building out Firemen’s Park.”

Crews discovered unmarked sanitary laterals, fiber optic lines, and electrical wires that were not in conduit, posing a safety hazard. They also unearthed improperly connected drain pipes and a water main buried less than four feet deep, far shallower than the typical five-foot requirement, which forced a halt to some utility work to ensure future designs met state codes.

“Basically we’ll have all the concrete done minus where that transformer is, middle of next week,” Phillips said. “And then we’ll have to wait for that transformer to be decommissioned to finish that the concrete in that area.”

The most significant external hurdle has been with ComEd. Project leaders said the utility company’s layoffs last year after a failed rate hike request created a massive backlog of work orders.

“We’ve been told hopefully we would have service in advance, but that has delayed some things,” Bergher said. “We’re still waiting on them. They were supposed to be here last Friday. They put us off yet again and we still do not have an answer.”

This delay has forced the construction team to work out of sequence, completing available tasks while waiting for permanent power to be installed. Goslin noted that contingency plans are being developed to use temporary power to irrigate the new fields if necessary.

Another challenge emerged mid-construction when the Monee Historical Society raised concerns about the accessibility of the adjacent Creamery building. The existing mechanical lift has been unreliable, and a request was made to add a permanent ADA-compliant ramp. Because concrete walkways were already poured, adding a concrete ramp now would require costly demolition or concrete pumping.

“We probably had $60-70,000 in just getting the concrete up into the area,” Goslin said. PSI is now exploring more cost-effective alternatives, including a pre-fabricated galvanized steel ramp system similar to those used in stadiums, which would require less site disruption.

Despite the delays, visible progress is being made daily. The storage building and volleyball courts are largely finished, needing only nets. Most concrete work for walkways and paths is expected to be complete within a week. At the baseball field, fences for the batting cages are up, the infield is graded, and backstops are in place. The football fields are graded, with final restoration and seeding planned as one of the last steps to avoid damage from remaining construction traffic.

Work on the interiors of the restroom and concession buildings is also advancing, with finishing elements like wall coverings, flooring, and fixtures being installed. Substantial completion is expected by August 11, which means the park will be functional and usable. The following two weeks, until the August 22 final completion date, will be dedicated to addressing a “punch list” of minor finishing touches.

During the presentation, Trustee Chuck Rakis questioned the fit and finish on the concession stand, pointing to photos showing rust on the bottom of metal panels. Goslin acknowledged the issue, explaining that a drip edge was causing water to flow back under the panels. “Yes, we are addressing that issue,” he assured the board. “We might be pulling that metal up and readjusting that lower flashing.”

Monee Weather Full forecast →
⚠️ Flood Advisory issued June 7 at 4:31PM CDT until June 7 at 7:30PM CDT by NWS Chicago IL
Today Jun 6
Showers And Thunderstorms Likely
84° 70°

Showers And Thunderstorms Likely

💨 5 mph 💧 57%

Latest News Stories

Meeting Briefs

Meeting Briefs: Will County Ad-Hoc Ordinance Review Committee for July 22, 2025

AI Policy Discussion Urged: Chair Jackie Triner called for the county to develop a comprehensive policy on the use of Artificial Intelligence. Citing a recent conference, Triner noted the potential benefits...
Monee Township Logo.1

Township Approves Funding for Youth Track Club and Support Services

Monee Township Board Meeting | June 19, 2025 Article Summary: The Board of Trustees approved social service agreements totaling nearly $7,000, with the bulk of the funding directed toward the Illinois...
Monee Township Logo.1

Monee Township Board Restructures Food Pantry to Secure Non-Profit Status

Monee Township Board Meeting | June 19, 2025 Article Summary: The Monee Township Board has initiated the creation of a separate legal entity for its food pantry to achieve 501(c)(3) status....
MONEE P&Z 7.16.25

Monee Zoning Board Recommends Approval for Sheepdog Firearms After Environmental Safety Review

Sheepdog Firearms, a gun shop and shooting range that has operated in the village for eight years, received a unanimous favorable recommendation for a special use permit from the Monee...
WCO-PZ-July-15

Crete Township Wins Approval for New Digital Sign at Community Center

Crete Township received approval from the Will County Planning and Zoning Commission on Tuesday for a new digital sign at its community center, a project that required a special use...
CM SB 7.15.25

Crete-Monee Board Debates Arming Security Director, Hears Comprehensive Safety Update

CRETE, IL – A comprehensive update on school safety at Crete-Monee School District 201-U on Tuesday culminated in a board-level debate over whether the district’s director of safety and security...
WCO-PZ-July-15

Will County Planners OK Oversized Garage Near Naperville, Overriding Staff Recommendation

The Will County Planning and Zoning Commission on Tuesday approved variances for a new oversized accessory garage in Wheatland Township, siding with a homeowner and builder over a staff recommendation...
CM SB 7.15.25

Crete-Monee to Name New Softball Field for Hall of Fame Coach Sue G. Antonio

CRETE, IL – A true Crete-Monee legend will be permanently honored at the district’s new athletic complex after the Board of Education unanimously voted Tuesday to name the softball field...
CM SB 7.15.25

Monee Elementary to Receive $172,000 STEM ‘Smart Lab’ Through Foundation Donation

Monee Elementary School will soon be home to a state-of-the-art STEM lab, thanks to a donation valued at approximately $172,000 from the Compost Foundation. The Crete-Monee Board of Education received...
WCO-PZ-July-15

Green Garden Landscaping Business Gains Permit Amid Strong Neighbor Support

A small landscaping and lawn maintenance business operating on a residential property in Green Garden Township received official approval Tuesday after neighbors voiced overwhelming support for the operation. The Will...
CM SB 7.15.25

Crete-Monee 201-U Renews E-Learning Plan for Emergency School Closures

CRETE, IL – The Crete-Monee School Board on Tuesday approved a three-year renewal of its E-Learning Plan, cementing the district’s strategy for handling emergency school closures like snow days without...
Meeting Briefs

Meeting Briefs: Will County Planning and Zoning Commission for July 15, 2025

Frankfort Shed Relocation Approved: A homeowner on West Harvest Drive in Frankfort Township received a variance to reduce an east side-yard setback from 10 to 4 feet. The variance, sought by...
Meeting Briefs

Meeting Briefs: Crete-Monee Board of Education for July 15, 2025

Construction Payments Exceed $4.9 Million: The board approved a series of large payments to construction firms for ongoing capital projects across the district. The payments, totaling over $4.9 million, include $3.1...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Approves ‘Whisk & Flame’ Culinary Studio, Slashes Parking Requirement for Downtown Property

An experiential culinary studio named Whisk & Flame is set to open in downtown Frankfort after the Village Board approved a series of special use permits and a significant parking...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Village Board Adopts $59.4 Million Appropriation for Fiscal Year 2026

The Frankfort Village Board has formally set its maximum legal spending limit for the upcoming fiscal year, adopting a $59,366,900 appropriation ordinance for fiscal year 2026. The measure was passed...