Firemen’s Park Nears Finish Line After Delays; August Opening Targeted

Spread the love

After months of anticipation and unforeseen challenges, the major renovation of Firemen’s Park is scheduled for substantial completion by August 11, with a final completion date of August 22, project leaders announced at the Monee Village Board meeting Wednesday.

Engineers and contractors detailed a series of setbacks that have delayed the park’s opening, primarily citing unmarked underground utilities and significant backlogs at ComEd.

“Everyone’s anxious to have Firemen’s Park open and ready and be operational, and we’re getting close,” said Matt Bergher, an engineer with Farnsworth Group, who presented alongside Justin Goslin, president of Piggush Simoneau, Inc. (PSI), and site manager Jason Phillips.

The project team described the park’s subsurface as a maze of unexpected obstacles. “Some of the things have been underground utility lines that are just not marked,” Bergher explained. “And also ones that were not known to exist underneath there just from years and years of building out Firemen’s Park.”

Crews discovered unmarked sanitary laterals, fiber optic lines, and electrical wires that were not in conduit, posing a safety hazard. They also unearthed improperly connected drain pipes and a water main buried less than four feet deep, far shallower than the typical five-foot requirement, which forced a halt to some utility work to ensure future designs met state codes.

“Basically we’ll have all the concrete done minus where that transformer is, middle of next week,” Phillips said. “And then we’ll have to wait for that transformer to be decommissioned to finish that the concrete in that area.”

The most significant external hurdle has been with ComEd. Project leaders said the utility company’s layoffs last year after a failed rate hike request created a massive backlog of work orders.

“We’ve been told hopefully we would have service in advance, but that has delayed some things,” Bergher said. “We’re still waiting on them. They were supposed to be here last Friday. They put us off yet again and we still do not have an answer.”

This delay has forced the construction team to work out of sequence, completing available tasks while waiting for permanent power to be installed. Goslin noted that contingency plans are being developed to use temporary power to irrigate the new fields if necessary.

Another challenge emerged mid-construction when the Monee Historical Society raised concerns about the accessibility of the adjacent Creamery building. The existing mechanical lift has been unreliable, and a request was made to add a permanent ADA-compliant ramp. Because concrete walkways were already poured, adding a concrete ramp now would require costly demolition or concrete pumping.

“We probably had $60-70,000 in just getting the concrete up into the area,” Goslin said. PSI is now exploring more cost-effective alternatives, including a pre-fabricated galvanized steel ramp system similar to those used in stadiums, which would require less site disruption.

Despite the delays, visible progress is being made daily. The storage building and volleyball courts are largely finished, needing only nets. Most concrete work for walkways and paths is expected to be complete within a week. At the baseball field, fences for the batting cages are up, the infield is graded, and backstops are in place. The football fields are graded, with final restoration and seeding planned as one of the last steps to avoid damage from remaining construction traffic.

Work on the interiors of the restroom and concession buildings is also advancing, with finishing elements like wall coverings, flooring, and fixtures being installed. Substantial completion is expected by August 11, which means the park will be functional and usable. The following two weeks, until the August 22 final completion date, will be dedicated to addressing a “punch list” of minor finishing touches.

During the presentation, Trustee Chuck Rakis questioned the fit and finish on the concession stand, pointing to photos showing rust on the bottom of metal panels. Goslin acknowledged the issue, explaining that a drip edge was causing water to flow back under the panels. “Yes, we are addressing that issue,” he assured the board. “We might be pulling that metal up and readjusting that lower flashing.”

Latest News Stories

Committee of teh Whole 8.12.25

Will County Board Gets Back to Basics with Robert’s Rules of Order Training

Article Summary: The Will County Board Committee of the Whole received a detailed training session on Robert's Rules of Order from parliamentary expert Matthew Prochaska to clarify procedures for conducting...
Exec Cmte 8.14.25.1

Executive Committee Approves Amended Houbolt Bridge Agreement to Settle Litigation

Article Summary: The Will County Executive Committee has approved an amendment to the Houbolt Road Toll Bridge agreement, formalizing a settlement between the bridge operators and the City of Joliet....
Meeting Briefs

Meeting Summary and Briefs: Will County Board Committee of the Whole for August 12, 2025

The Will County Board’s Committee of the Whole dedicated its August 12 meeting to an in-depth training session on Robert’s Rules of Order, aiming to foster more efficient and orderly...
Meeting Briefs

Meeting Summary and Briefs: Will County Ad-Hoc Ordinance Review Committee for August 12, 2025

The Will County Ad-Hoc Ordinance Review Committee advanced several updated chapters of the county’s public works code during its August 12 meeting, addressing topics from solid waste to waste hauler...
Screenshot 2025-11-26 at 7.30.24 AM

Monee Board Approves $1.7 Million Payment for Critical Water Main Redundancy

Village of Monee Board Meeting | August 13, 2025 Article Summary: The Monee Village Board authorized a substantial payment of over $1.7 million to Iroquois Paving for the Ridgeland and...
WCO-Landfill-8.5.25.2

Report Finding Few Trucks Littering Sparks Debate on Cleanup Responsibility

Article Summary: A Will County report found that a very small percentage of waste-hauling trucks are the source of litter on roadways near the county landfill, sparking a debate among...
crete-monee school district graphic.3

Crete-Monee Spotlights Summer School Success with STEM, Arts, and Academic Gains

Article Summary: The Crete-Monee school district’s 2025 summer school program was a major success, serving nearly 500 students with a blend of academic support and hands-on enrichment activities, including robotics,...
crete-monee school district graphic.2

Crete-Monee School Board Tables Vote on Arming Security Director Amid Debate

Article Summary: A proposal to allow Crete-Monee 201-U’s Director of Safety and Security to carry a firearm on school grounds was tabled by the Board of Education following a lengthy...
WCO-Landfill-8.5.25.1

Will County Receives Detailed Update on Landfill Expansion Investigation

Article Summary: The Will County Landfill Committee received a comprehensive technical update on the site investigation for the planned horizontal expansion of the county landfill, confirming the project remains on...
Meeting Briefs

Meeting Summary and Briefs: Will County Landfill Committee for August 7, 2025

The Will County Landfill Committee on Thursday heard a detailed technical update on the ongoing investigation for the county landfill expansion, confirming that the complex project remains on schedule. Consultants...
crete-monee school district graphic.1

Crete-Monee 201-U Board Reviews Tentative Budget with Projected $722,000 Deficit

Article Summary: The Crete-Monee School District 201-U Board of Education reviewed a tentative 2025-2026 budget that projects a $722,209 operating deficit, driven largely by a nearly $2.75 million reduction in...
Green-Garden-Logo.WP

Green Garden Township Moves Forward with New Town Hall Plans, Awaits Grant Approval

ARTICLE SUMMARY: Green Garden Township is advancing with preliminary work for a new town hall, having met with architects and a civil engineer, while awaiting Will County's final approval to...
Green-Garden-Township-Graphic.1

Township Board Approves Budget Transfers to Fund Assessor’s Staff and Correct Rent Payment

ARTICLE SUMMARY: The Green Garden Township Board approved Resolution 2025-005, which reallocates a total of $25,200 within the town fund to provide necessary staffing funds for the assessor's office and to...
solar panels photovoltaics in solar farm

County Rep Cites Solar Lawsuits, Grant Shortfalls as Key Issues Facing Will County

ARTICLE SUMMARY: Will County Board member Sherry Newquist reported that the county is navigating lawsuits related to solar farm approvals and anticipating budget challenges from the loss of federal grant money....
Assessor

Assessor’s Office Hires Staff to Handle Workload After 6% Multiplier Hits Property Owners

ARTICLE SUMMARY: Following the application of a 6% property assessment multiplier across Green Garden Township, the assessor's office has hired a new staff member to help manage the increased workload and...